On 28 May RWCS had a meeting with MD of Electricity Department and the problems relating to power supply & frequency of fluctuations were discussed. Sub sequently there were discussions with the SDO Mr. Biswajit who assured us that soon the problems of our sector will be resolved.
Following maintenance works have been planned:
1) Old and faulty VCB panel will be changed with a new panel of feeder number 8 (feeder B block and partially A, C and D block) by today itself.
2) Overloaded 250 Kva transformer at A- 93 will be replaced with higher capacity 400 Kva transformer within a week.
3) All old and rusty poles will be replaced with new poles after having a discussion with RWCS team within 20-25 days.
4) Old and damaged conductor will be replaced with new conductor after having a discussion with RWCS team within 20-25 days
All above work’s estimate has been approved and sanctioned by discom headquarter.
All these works will be done in upcoming days in sector 26 for improving power supply quality. All the work has been approved and sanctioned by discom headquarter.
Popular Stories
How To Revive Your Rainwater Harvesting System
The Water Couple’s Journey: From Cleaning Tanks to Complete Water Solutions!
Locals Felling Trees Near Sec A Pkt C
Winning Has Become a Habit for Divya
Is Green Park Heading Towards A Slum
Haphazard Parking, Narrow Walking Space In M Block Market
Recent Stories from Nearby
- Bura Na Mano, Holi Hai!!! April 4, 2025
- Water Wastage: A NegligenceWe Can No Longer Ignore April 4, 2025
- Residents Take Up Empty Plot Cleaning & Installation of Composting Pits April 4, 2025
- AIKGA Holds 58th Fruit, Vegetableand Flower Show (2025) April 4, 2025
- Reckless Driving: Norm Of The Day April 4, 2025